paging Nautilus ????????????????
it is in Boston, its york air cooled water chiller theres also 3 boilers that need to be done, i can do the breaching. i think it was 16 condo units.
i need a price, and if i get the job, i would need the install.
i know its far, but not sure if you would want it. carry for hotel rooms ect.
let me know. the price is do the 25 i think i will send a set of prints.
it is in Boston, its york air cooled water chiller theres also 3 boilers that need to be done, i can do the breaching. i think it was 16 condo units.
i need a price, and if i get the job, i would need the install.
i know its far, but not sure if you would want it. carry for hotel rooms ect.
let me know. the price is do the 25 i think i will send a set of prints.
I'll talk with my dad tonight about it. Normally we would be very intrested... the problem is right now we are slammed and way under staffed for the work on our plate right now... Whats the time line for construction? Is this something they are pushing or basically when would we need to be in boston? Let me know and I'll get back to you tomorrow or sunday.
right now i have no one capable of doing the chiller work, so if you cant do it. im not going to bid any of it.
the timeline is start date within 30 days of the award of contract, then it will go from there. no schedual yet so im not sure how long it is.
it is a rate job, and subject to "the boston plan". im looking into that now. it might be somthing we may not want.
im on hold now. will let you know.
we may not need the plumbing, but i will still send it in if you want.
let me know.