VE Spreadsheet
http://www.tditechnology.com/VE-Calculator.xls
Last edited by 99FormulaWs6; Aug 9, 2005 at 11:44 AM.
edit:
now that I've downloaded it, it looks very similar to the spread sheet I used a while back. Nice work! your's is much more a finished product than mine
Trending Topics
The Best V8 Stories One Small Block at Time
1. On the Calculation Sheet: The formula you're using is LTFT - STFT / 2 to get the %
change on the VE Table. Don't you want LTFT + STFT / 2 ?
2. On the New VE Table Sheet: The formula you're using is Current VE Value - Calculation Sheet Value. Again, don't you want Current VE Value + Calculation Sheet Value?
The problem I've noticed is if you have negative fuel trims. Let me show an example:
Say you have a LTFT value of -10, a STFT value of -5, and a Current VE of 50
Calculation Sheet: LTFT - STFT = % VE Change, (-10) - (-5) = -5
New VE Table Sheet: Current VE - Calc Sheet Value = New VE, (50) - (-5) = 55
The problem I see is that if the car is pulling fuel you want to lower the VE and these calulations end up raising it.
Same values using the 2nd formulas:
Calculation Sheet: LTFT + STFT = % VE Change, (-10) + (-5) = -15
New VE Table Sheet: Current VE + Calc Sheet Value = New VE, (50) + (-15) = 35
Obviously I just pulled these values out of the air, but the calculations are valid (I think). Sorry this is hard to follow, but let me know if I'm on the right track or totally wrong. Thanks!
OrangeWs6 it won't work in Edit, because you need a Data logger with the histogram function.

Thanks,
Jason